AES · Company KPIs

AES (AES) KPIs

Backlog of signed PPAs (projects with signed contracts not yet operational), Backlog under construction. As reported in SEC filings, with the source line for each figure.

Backlog of signed PPAs (projects with signed contracts not yet operational)

11.1 at Sep 30, 2025

Dec 31, 2024: 11.9Mar 31, 2025: 11.7Jun 30, 2025: 12Sep 30, 2025: 11.1Dec 31, 2024Sep 30, 2025

The filings read for this page do not define this measure.

Backlog of signed PPAs (projects with signed contracts not yet operational), as first reported, with the line it was read from
Period endedFigureFiling text
Sep 30, 202511.1•PPA backlog of 11.1 GW, including 5 GW under construction8-K filed 2025-11-04
Jun 30, 202512The Company's backlog, which consists of projects with signed contracts, but which are not yet operational, is 12 GW, including 5.2 GW under construction.8-K filed 2025-08-01
Mar 31, 202511.7The Company's backlog, which consists of projects with signed contracts, but which are not yet operational, is 11.7 GW, including 5.3 GW under construction.8-K filed 2025-05-01
Dec 31, 202411.9The Company’s PPA backlog, which consists of projects with signed contracts, but which are not yet operational, is 11.9 GW, including 4.9 GW under construction.8-K filed 2025-02-28

Backlog under construction

5 at Sep 30, 2025

Dec 31, 2024: 4.9Mar 31, 2025: 5.3Jun 30, 2025: 5.2Sep 30, 2025: 5Dec 31, 2024Sep 30, 2025

The filings read for this page do not define this measure.

Backlog under construction, as first reported, with the line it was read from
Period endedFigureFiling text
Sep 30, 20255•PPA backlog of 11.1 GW, including 5 GW under construction8-K filed 2025-11-04
Jun 30, 20255.2The Company's backlog, which consists of projects with signed contracts, but which are not yet operational, is 12 GW, including 5.2 GW under construction.8-K filed 2025-08-01
Mar 31, 20255.3The Company's backlog, which consists of projects with signed contracts, but which are not yet operational, is 11.7 GW, including 5.3 GW under construction.8-K filed 2025-05-01
Dec 31, 20244.9The Company’s PPA backlog, which consists of projects with signed contracts, but which are not yet operational, is 11.9 GW, including 4.9 GW under construction.8-K filed 2025-02-28

Reading notes

Figures are shown as first reported. If a later filing prints a different figure for the same period, both appear. A figure marked ≈ or shown in words is how the company itself states it, not an estimate of ours. Companies change definitions over time, so compare periods with the quoted definition in mind. Periods that failed our checks are left out, so gaps are expected.